Project Description
BuildersRig Construction Inc extensive experience working within heavily congested utility locations, as well as our ability to perform gas and steam work directly, was critical to the early completion of this complex project.
Overall, the project installed 3,400 LF of distribution water main, 1,990 CY of concrete road base and 6,200 SY of asphalt pavement.
Riverfront Renewal Initiative
Serving the New York City Department of Parks & Recreation
BuildersRig Construction Inc was tasked with reconstructing the deteriorated 4Riverfront Renewal Initiative outfall along the East River in Long Island City.
East River Pier Construction Scope
The outfall construction work included removing the pier deck and timber piles, driving new concrete-filled open-end pipe piles, placing a new structural steel framework, and placing a new concrete deck slab. BuildersRig Construction Inc also replaced a 66-inch sewer outfall with a new reinforced concrete pipe and poured-in-place concrete encasement.
What is Outfall Construction or Marine Outfall Construction?
An outfall in general is the “discharge point of a waste stream into a body of water; alternatively it may be the outlet of a river” where it discharges into the sea, a lake or the like. A marine outfall is a pipeline or tunnel that discharges municipal, storm water or other waters to the sea.