WaterWorks Avenue Initiative 7th Street
For the New York City Department of Design and Construction and Waterworks JV – MED609(610) , BuildersRig Construction Inc installed approximately 1,800 LF of 36” welded steel water main in the historic West Village connecting to shaft 27B. The water main work also included the installation of 36” flow meters, 36” butterfly valves, 24” regulator valves, blow-offs, air cock hydrants and their appurtenant chambers.
BuildersRig Construction Inc also performed extensive private utility relocation and capital work in conjunction with the water main installation.
Other Med609 project related work see 9th Avenue Gas Main Installation
Contracting Agency
NYCDDC and Waterworks JV
Project Title
WaterWorks Avenue Initiative 7th Street
Project Location
New York, NY
Contract Amount
$10,250,000
Project Description
BuildersRig Construction Inc installed approximately 1,800 LF of 36” welded steel water main in the historic West Village connecting to shaft 27B.
The water main work also included the installation of 36” flow meters, 36” butterfly valves, 24” regulator valves, blow-offs, air cock hydrants & their appurtenant chambers.
In addition, BuildersRig Construction Inc performed extensive private utility relocation and capital work in conjunction with the water main installation.
Then they installed 1,500 linear feet of water mains with diameters ranging from 6" to 20".