top of page
Construction Site
reconstruction

Canal Street Reconstruction

Roadway Reconstruction Project

The Canal Street reconstruction project is a joint bid, mass excavation project intended to install a new trunk water main between Hudson Street and Park Row. BuildersRig Construction Inc  won a competitive contract bid (HWMWTCA7E). The NYC DDC (New York City Department of Design and Construction see also NYC DDC Wiki) contracted our work.  This critical installation is part of the City’s ongoing efforts to improve the distribution of water throughout Lower Manhattan.

Contracting Agency

NYC Department of Design & Construction

Project Title
Project Location

Reconstruction of CCanal Street

Manhattan, NY - Canal Street

Contract Amount

$80 Million

Project Description

Connected to the already installed water system shaft to the west at Hudson Street, a series of 48" and 36" diameter steel trunk mains are being installed below Worth Street, to become part of one of the most complex water systems in the world.

Extensive Reconstruction work along MTA subway tunnels

As part of this project, BuildersRig Construction Inc  has also been tasked with replacing aged water mains, sewers, street lights, traffic signals, curbs, sidewalks, roadway construction plus private utilities throughout. The extensive limits of the project traverse five MTA subway tunnels actively serving 13 subway lines. This is a unique challenge, along with coordinating work around active utility facilities, including natural gas, steam, electric, telephone and fiber lines.

Reconstruction Safety

During this project, BuildersRig Construction Inc  successfully and safely maintains access to buildings, driveways, businesses, subway entrances and other various needs of the surrounding community.

Roadway Construction combined with complex Utility Infrastructure

BuildersRig Construction Inc  extensive experience working within heavily congested utility locations, as well as our ability to perform gas and steam work directly, provides invaluable benefit to both the project’s performance and schedule. Overall, the project plans to install 4,500 LF of steel trunk water main, 6,500 LF of distribution water main, 4,800 CY of concrete road base and 20,000 SY of asphalt pavement.

bottom of page